Rites revises estimate for Northeast Frontier Railway electrification to Rs 532 crore
The revised total cost for the project stands at Rs 531.77 crore, excluding GST, which marks an increase from the original cost of Rs 288.44 crore.
Rites revises estimate for Northeast Frontier Railway electrification to Rs 532 crore
State-run Rites informed that it has received a revised estimate of Rs 532 crore for an electrification project under the Northeast Frontier Railway. The revised total cost for the project stands at Rs 531.77 crore, excluding GST, which marks an increase from the original cost of Rs 288.44 crore.
The electrification work is to be carried out on a turnkey basis at the Lumding junction and Badarpur junction section of the Lumding division of Northeast Frontier Railway, it added.
The company’s consolidated net profit declined 27.84% to Rs 72.98 crore in Q2 FY25 as against Rs 101.15 crore recorded in Q2 FY24. Revenue from operations fell 7.12% to Rs 540.86 crore in the quarter ended 30 September 2024 from Rs 582.36 crore posted in Q2 FY24. The Shares of Rites rose 0.49% to end at Rs 275.20 on the BSE on Friday.
Read Also : Union Minister Shri Manohar Lal visits 45 MW NHPC Nimoo Bazgo Power StationNews Must Read
- Rites revises estimate for Northeast Frontier Railway electrification to Rs 532 crore
- Central Bank of India gets approval for insurance JV with Generali Group
- CSL signs MOU with Seatrium Letourneau USA, to develop jack-up rig design
- RBI inflows Rs 25,000 crore to boost system liquidity in banking system
- RVNL Fined by NSE and BSE for Board Composition
- Possible Collaboration between NLC India and Kerala State Electricity Board
- BEML wins BH60 Rear Dump Trucks worth of Rs 247 crore
- Navaratna PSU stock: Railtel bags order worth Rs 9.93 crore, shares rises above 1.4%
- PSU Honor: Power Ministry awarded First Prize to SJVN
- NLC India Limited Contributes Rs. 1 Crore to Kerala Disaster Mitigation Fund