EIL at Vizag Refinery Modernization Project of HPCL installed 1st piperack module at RUF unit
RUF unit is being implemented for the 1st time in India and is also the largest and most complex package of VRMP.
New Delhi: Team EIL at Vizag Refinery Modernization Project of HPCL achieved a key milestone with the successful installation of 1st piperack module at its Residue Upgradation Facility (RUF) unit.
RUF unit is being implemented for the 1st time in India and is also the largest and most complex package of VRMP.
The modularization concept involves meticulous planning, detailed Material planning & procurement, careful logistics plan and execution strategy and have several advantages over conventional execution e.g. increased safety and quality as fabrication and erection of structure & piping are done under controlled conditions, minimizing the requirement of onsite material storage and wastage of materials besides schedule advantage which offsets the costs involved in comparison to conventional execution.
Read Also : NALCO Q2 FY25 results: Net Profit zooms, announced dividendNews Must Read
- NALCO Q2 FY25 results: Net Profit zooms, announced dividend
- MRPL Receives Special Award at Energy Technology Meet
- GRSE announced Q2 & H1 FY25 Results
- DBS Bank India CEO To Retire
- SBI, HDFC Bank and ICICI continue as RBI's Systemically Important Banks
- AK Sahney appointed as Chairman of IOCL
- GIC Re Q2 results: Net profit rises 16% to Rs 1,860.76 crore
- MOPNG Curtain Raiser for Bihar
- Public Sector Banks show strong performance in First Half of FY 2024-25
- Power Grid acquires transmission Project in Rajasthan through TBCB