Agra Metro Rail Project: Achieved milestone in just 77 days
New Delhi/Agra: Agra Metro Rail Project achieved a significant milestone as TBM 'Yamuna' completed the 440-meter-long tunnel connecting the upcoming underground Jama Masjid metro station with Agra Fort metro station in just 77 days, making it the fastest breakthrough achieved by any metro project in the country.
Read Also : THDC India Limited Commemorates Constitution Day with Enthusiasm and ReverenceThe tunneling work on the priority corridor's 3 km underground section between Taj Mahal and Jama Masjid started in February 2023. The tunneling work linking Ramlila Maidan with Agra Fort Metro Station as part of the Agra Metro Rail Project has also been completed.
The machine built 239 rings (334m) from the crossover at Ramleela Maidan to Agra Fort in 77 days. The 29.4 km Agra Metro has two corridors with 27 stations. The commissioning of the Priority Corridor is expected to meet the August 2024 deadline.
Read Also : RummyCircle Introduces the Thrill of 5-Minute Rummy!
The Uttar Pradesh Metro Rail Corporation (UPMRC) officials claim it to be a major breakthrough in record time, and they are committed to giving the people of Agra a world-class metro by March 2024.
Read Also : 75th Constitution day observed at nlc india limitedNews Must Read
- BEML and MDL signs MoU for developing Marine Applications
- Ravi K Takes Over as Director (Operations) at HAL
- REC Limited bags award in Best Corporate Film category
- Paytm Launches UPI LITE Auto Top-up for Recurring Daily Payments Under Rs 500 with No PIN
- SECI sign MoU with Rajasthan Government for investment in Renewables
- Power Minister inaugurates NTPC Green Hydrogen Mobility Project in Leh
- Rites revises estimate for Northeast Frontier Railway electrification to Rs 532 crore
- Central Bank of India gets approval for insurance JV with Generali Group
- CSL signs MOU with Seatrium Letourneau USA, to develop jack-up rig design
- RBI inflows Rs 25,000 crore to boost system liquidity in banking system