DMRC completes 4 KM construction of viaduct on Janakpuri West – RK Ashram Marg corridor
DMRC completed 2.2 kilometers of underground tunnels (for up and down movement) between Janakpuri West and Krishna Park Extension on this corridor last year.
New Delhi: The Delhi Metro Rail Corporation (DMRC) has successfully completed the structural work of four kilometres of viaduct starting from Majlis Park to Mukarba Chowk connecting the Majlis Park and Bhalaswa Metro stations on the upcoming Janakpuri West – RK Ashram Marg corridor of Phase 4.
This particular completed stretch of the elevated viaduct is now being offered to the system contractors for track laying and traction work involving the erection of Over Head Electrification (OHE) masts etc. The structural work for the viaduct shall also be completed till Haiderpur Badli soon, as just a crossing over a railway track is left there.
This is an important achievement for DMRC’s engineers since the work on this corridor had started amidst the Covid crisis and had to face intermittent delays due to the pandemic, and issues pertaining to obtaining tree-cutting clearances. The construction work of this corridor shall be completed by March 2026. This work was completed without causing any major disruption to the flow of traffic below.
Join PSU Connect on WhatsApp now for quick updates! Click here
Read Also : SJVN’s Rampur Hydro Power Station Beats Target by 3 MonthsWork on the Janakpuri West – RK Ashram Marg Metro corridor is progressing at full speed now. DMRC completed 2.2 kilometers of underground tunnels (for up and down movement) between Janakpuri West and Krishna Park Extension on this corridor last year. On the 2nd of June earlier this week, another tunnel boring machine was lowered for tunnelling work between Derawal Nagar to Pulbangash.
This TBM drive will achieve depth upto 25.9 metres near the Najafgarh drain and will be 5800 metres in dia. The movement of the TBMs are being monitored round the clock digitally by DMRC since there are a lot of old buildings above.
Read Also : Bhutanese Delegation Visits at THDCIL's VPHEP Project
As part of its Phase 4 expansion, DMRC is currently engaged in the construction of 65 kilometres of new lines across three different corridors. Out of these 28 kilometres will be underground and the rest shall be elevated. 11 new interchange stations shall also come up as part of this new expansion.
Read Also : Abhijit Majumder appointed as CFO at Oil India LtdNews Must Read
- SJVN’s Rampur Hydro Power Station Beats Target by 3 Months
- Bhutanese Delegation Visits at THDCIL's VPHEP Project
- Abhijit Majumder appointed as CFO at Oil India Ltd
- RITES bags Major order of Rs. 122.60 Crores
- Coal & Lignite Public Sectors establishes 16 Eco-Parks over last 5 years to promote tourism
- BEML and NHPC Ltd Sign MoU for Hydroelectric Power Plants
- No plans for ONGC Green Limited listing said ONGC
- BSNL India and NIST University signed an MoU
- Powergrid Signs Two MoUs with Haryana State CSR Trust
- MRPL and ONGC Signs MoU