New Delhi: Balram opencast project of Mahanadi Coalfields Limited (MCL) completed two weeks of no production due to stalemate between Danara and Solada villages at Talcher coalfields in Angul district of Odisha.
Up till now, 2.2 lakh tonne coal supply, around 1.8 lakh tonne coal production and more than 4 lakh cubic meter of over burden removal has been affected from Balram OCP due to the internal rift of two villages.
Series of initiatives taken by the civil administration and MCL management have failed to mend the differences between the villagers of Solada and Danara, who have forcibly stopped mining operations at Balram OCP.
While production from other coal mines have started picking up after rainy season, but the Balram OCP, having a target of six million tonne coal production for 2019-20, remained paralysed due to villagers’ internal rift.
The company hopes that an amicable solution to the impasse is reached so that further losses to various stakeholders, including the government exchequer, are arrested.
Read Also : Engineers India Paves the Way for Oil & Gas Sector Indigenization
News Must Read
- SJVN CMD Geeta Kapur Inaugurates Construction Works at Sunni Dam Project in Himachal Pradesh
- PESB Selects R Veerabahu as Director (Finance) for Braithwaite & Co. Limited
- Grew Energy bags largest order of 200 MW Contract of SECI's Auction
- CPCL Reports 39% YoY Drop in Q4 Net Profit, Declares Rs 55 per Share Dividend
- SJVN Limited inaugurates India's first Multi-purpose Green Hydrogen Pilot Project
- KRDCL, RVNL JV emerges as the Lowest Bidder for Redevelopment of Thiruvananthapuram Central Railway Station
- REC Ltd. has incorporated subsidiary company BPTL
- Hon’ble Vice President of India Confers `Outstanding PSU of the Year’ Award on HAL
- BharatPe Launches India’s first All-in-One Payment Device
- NBCC registers historical Performance in FY2023-24